PROBLEM 1: CALCULATE SCHEDULE VARIANCE FROM EARNED VALUE CALCULATIONS FROM A 4 MONTH PERIOD.PLANNED VALUE (PV): 38 EARNED VALUE (EV): 30 CALCULATE SCHEDULE PERFORMANCE INDEX: CALCULATE ESTIMATED TIME

PROBLEM 1: CALCULATE SCHEDULE VARIANCE FROM EARNED VALUE CALCULATIONS FROM A 4 MONTH PERIOD.

PLANNED VALUE (PV): 38

EARNED VALUE (EV): 30

CALCULATE SCHEDULE PERFORMANCE INDEX:

CALCULATE ESTIMATED TIME TO COMPLETION:

PROBLEM 2: CALCULATE COST VARIANCE FROM EARNED VALUE CALCUATIONS WHERE PV = 38.

ACTUAL COST OF WORK PERFORMED (AC): $40,000

EARNED VALUE: 30

CALCULATE COST PERFORMANCE INDEX:

CALCULATE ESTIMATED COST TO COMPLETION:

Show your complete work with formulas and equation (calculations). Without complete and very step calculations and substitution of showing formulas and calculations, your assignment would be considered zero.

 