Engineering Homework Help. HW Question
Provide pricing for trash enclosure in LEMSO format – Blank excel file provided.
Given Information:
For labor use $50/hr
Excavation 2 CF per Wheel Barrow 10 minutes per wheel barrow
Formwork Labor 10 LF per hour (2 man crew)
Formwork material $1 per LF
Base $15 per ton material 110 lbs per CF
8x8x16 block $.97 each
8x8x8 block $.99 each
Concrete $100 per CY
Masonry Grout Labor included in wall labor cost but add $100 per CY for material
Wall Cap Material $5 per LF Install eight each 24″ pieces per HR (2 man)
USE MEANS RATES FOR MASONRY AND CONCRETE LABOR (don’t forget city index)
Rebar #4 Material cost $6.35 per 20 LF
Rebar #5 Material cost $9.87 per 20 LF
Rebar Labor MEANS rate of $740 per ton (be sure to add for City Index)
Use a subcontract value of $1,500 for the metal gate, posts and hardware.